"The costs of building the Turner Centre, Kent's flagship arts centre, have spiralled to nearly £30 million- about four times the original cost, it has emerged.
It has also been revealed that the centre, being build alongside the stone pier at Margate, is now expected to open in the first six months of 2008, four years later than first forecast.
And in a further blow, KCC said that it was still about £9.8 million short of what it needed to build the distinctive gallery, which will be partly bedded in the sea"
Source- Isle of Thanet Extra, 28/10/2005
By my calculations, assuming interest rates of 4% and an admission charge of £10, the Turner Centre will need 300 vistors PER DAY just to cover interest charges, before it can even think about covering operating costs. It is madness that we have a site like Dreamland Park, capable of pulling in visitors in the hundreds of thousands every year, and that we are fighting to save that, while a fortune is being thrown away to build the Turner Centre which will remain forever a liability to Kent taxpayers.