by Chief Engineer » 15 Apr 2011, 23:24
Hi everyone,
Soon, very soon, I will keep you posted on when the opening day will be, still a lot to do.
As the pictures show all the main structure and track are in place and hopefully the start of next week should see a lot of the pneumatics and electrical systems put in place, by mid week hopefully you should see a couple of cars making an appearance, then its a few days of testing to make sure everything is working how it should.
But you don't have to take my word that it will all working correctly, the ride is then inspected by three independent engineers, each engineer inspects and tests the different engineering, structural, electrical and control systems that make up the ride, this also includes all the structural tests carried out over the winter period when the ride was in its component parts, once they are satisfied that all is correct the ride will be issued an 'Initial Test' along with a 'D.O.C' that annually each ride has to obtain for the Pier to open the ride to the public, same as a MOT on a car.